With the foundation complete, stone masonry plinth walls went up — and came in higher than originally planned, well over 4 feet. The technique used is locally called Kalache Bandhakam: the stonework is left rough below ground, and the same wall gets a finished, dressed face above ground.

That extra height opened up a possibility. The build needed underground water storage with 7 days of capacity. Rather than digging a separate pit elsewhere on the plot, the tank was built directly under the courtyard, using the space the taller plinth already created.

Status
Plinth beam work is now the focus, building on top of these walls.
See the journal entry for the full write-up, including a walkthrough video of the finished plinth.