Methods

  • Mechanical earth cutting with JCB
  • Topsoil preservation for regeneration
  • Depth verification against foundation plan
  • Complete excavation of small block areas (bathrooms, etc.)

Materials

  • Excavated earth (stockpiled on-site)

Earth cutting to the required depth for the foundation phase. The ground surface at Gorhe Khurd was not soft — excavation by hand was not possible, and a JCB was used instead.

JCB loading excavated earth during site excavation

Because the strata were hard and rocky, the machine dug broader pits than a careful hand cut would have produced. Small block areas such as bathrooms were fully excavated at this stage.

Broader excavation pits dug through hard, rocky ground

Topsoil was carefully separated and stockpiled for later landscaping and planting. Excavated subsoil is retained on-site for use in compressed stabilized earth blocks (CSEB) and other earth-building applications — embodying the zero-waste construction principle.

See the journal entry for the full write-up from this phase.

Lessons Learned

  • Set aside topsoil immediately — it cannot be recovered once mixed
  • Test soil at depth before finalizing foundation design
  • Hard ground may require machines — budget for broader pits than hand digging
  • Confirm whether hand excavation is feasible before committing to a method